Appearance Inspection Method Of Constant Force Spring Hangers

Sep 01, 2025

Leave a message

Appearance inspection method:

Under normal natural light or 40W fluorescent lamp in the room, the illumination of light is not less than 300lx, and visual inspection is carried out at a distance of 500mm from the test piece. It is allowed to select truly representative parts from the series of constant force spring hangers with the same structure, the same material, and the same process as the test piece for testing. If the test is qualified, it is considered that the series of product parts with the same structure, the same material, and the same process are qualified. Test quantity, test quantity: 1. Adhesion tester or new No. 11 surgical blade is used, and the surgical blade should meet the requirements of GB2544. During the grid test, the blade is perpendicular to the surface of the constant force spring hanger, and the force is even and the speed is steady. Four scratches are cut vertically and horizontally on the flat paint film to the surface of the substrate without vibration, forming 9 small squares, and the area of each square is 1mm2. T9286), detect the peeling of the paint film. And record the test results.

Make the load evenly distributed and pull out the locking pin 14 one by one.

If the above method has been adjusted, but the locking pin still cannot be removed, the relevant technical personnel should be asked to review whether the load selection of the support and hanger is reasonable and whether the support and hanger number should be changed.

1 VHDE and HHDE type constant force spring support and hanger are rooting plates connected to the steel structure with double bolts, as shown in Figure 8.

2 The locking pin 14 pulled out after the load adjustment should be stored in the pin storage hole 9, and it is strictly forbidden to insert it into other holes.

3 When the support and hanger load is adjusted, it is not allowed to cut off the locking pin 14 with flame. 4.4 When the support and hanger load is adjusted, it is not allowed to use a heavy hammer to hit the locking pin 14.

5 The spring fastening nut 11 shall not be adjusted without the permission of the company.

6 After the pipeline and equipment are in normal operation, the position of the support and hanger displacement indicator 7 must be checked frequently and recorded. The displacement indicator is in normal state.