Constant force spring supports and hangers are supporting and hanging devices used for installing pipelines, heating, ventilation and air conditioning equipment, etc. They are mainly made of carbon steel or stainless steel, and feature large suspension weight, flexible adjustment, good shock absorption performance, etc.
The installation method of constant force spring supports and hangers is as follows:
I. Preliminary Preparation
Before carrying out the installation work of constant force spring supports and hangers, preliminary preparations are required. Firstly, it is necessary to inspect the construction area to understand the installation conditions, such as the size, height, ambient temperature, air flow of the space, etc. Meanwhile, it is also necessary to check the preparation of equipment and tools.
II. Formulating Installation Plan
Formulate an installation plan according to the actual situation, including the position, quantity, spacing of supports and hangers, as well as the hoisting height, etc. The plan should be scientific and reasonable to ensure that the weight borne by the supports and hangers is evenly distributed and their positions are accurate.
III. Cleaning Before Installation
Before installing the constant force spring supports and hangers, it is necessary to clean the installation area and equipment to ensure that there is no dust, oil stains and other substances that may affect the installation effect of the supports and hangers.
IV. Determining the Position of Supports and Hangers
According to the formulated installation plan, determine the position of the supports and hangers, drill holes in fixed points such as walls and ceilings with special tools, and then install gusset sockets or hanger pressure plates.
V. Fixing the Supports and Hangers
Fix the constant force spring supports and hangers to the fixed points through the assembly of gusset sockets or hanger pressure plates, then check whether the hoisting height of the supports and hangers is correct to make it consistent with the installation plan.
VI. Adjusting the Position of Supports and Hangers
After the installation is completed, check whether the hoisting height of the constant force spring supports and hangers is correct. If any problem is found, adjustments need to be made.
VII. Installing Pipelines or Equipment
Before installing pipelines or equipment, it is necessary to inspect the constant force spring supports and hangers to ensure they are stable and reliable. Then install the pipelines or equipment on the constant force spring supports and hangers, and tighten the bolts or screws.
VIII. Checking the Installation Effect
After the installation of the constant force spring supports and hangers is completed, an inspection is required to ensure that the installation effect meets the requirements. Such aspects include whether the position of the supports and hangers is accurate, whether the installed equipment or pipelines are stable, and whether the constant force springs have the load-bearing capacity, etc.